During the demolition of Phase 4 of the Woodbury Down Regeneration some traffic diversions will be in place.
Exactly when these will happen has not been definitely decided yet but WDCO has seen a presentation describing the construction logistics.
The erection of the hoarding around the site has already begun. Pavements to the North and South of the site have been closed. The bus stop on Seven Sisters Road will be suspended.
Woodberry Grove will be closed for some of its length and will become one way. Construction traffic will use the closed part as their access route to the construction site.
Cars, delivery lorries, bin men etcetera will be diverted through Goodchild Road and Kayani Avenue.
When will this happen?
The approximate dates are shown in this document, but may be subject to change, depending on permissions and progress. There are also contact details for the Berkeley Homes Senior Project Manager
20250918-presentation-to-board